Waterline Modification
by
Carla Whitmire
| Jun 11, 2012
On the Saturday of Memorial Day weekend this crew relocated an existing 8 inch waterline that was going to be underneath a proposed structure. This was the only time available to perform the task due to the fact that there were 2 office buildings that wouldn't have water service and would have to be shut down if this work was done any other time. Everything went as planned and there were no problems when the domestic and fire service to the existing buildings were re-pressurized.